In 2013 LiWooD won an EU-wide tender to construct and design 3 buildings for 265 students. The tender was based on a range of criteria which prioritised factors such as energy costs, maintenance, quality of materials, sustainability and cost. (The buildings were completed and ready for occupation within 6 months from start to finish).

  • 7.610 m²
  • Completion: 2013
  • Construction period: 6 months from foundation slab upwards
  • Air-water-heat pumps, photovoltaic
  • Energy efficiency: KfW40
  • 158 Apartments
  • For 265 students